Tag Archives: Mani

Design Update

Wednesday, 12 June 2013 So we gave our feedback to the initial design on Tuesday, 11 June 2013 and ACP Mani of Adodis Technologies sent us an update the following day. At this point we were happy with the responsiveness of ACP and had no reason to believe that our project would be delayed or… Read More »

False Progress

Monday, 10 June 2013 Today, our project manager ACP of Adodis Technologies sent us a screenshot of the initial design for our webpage. We were excited to see progress after when we were initially concerned that nothing had been accomplished after the past week. We gave some feedback and sent our response feeling optimistic that… Read More »

We Understand Everything…We’ll Start Next Week

Thursday, 06 June 2013 After submitting our scope of work to Adodis Technologies on Monday, 03 June 2013, we were contacted a couple days later asking us to come online to Skype.  This is the first time we were introduced to the project manager ACP Manivannan (also known as ACP or Mani). The initial email… Read More »